Herring Creek

Construction Status: 
pumpstations complete, Pinewater under construction, Banks Road ready for bid
Financing Status: 
Phase III financing accepted
Funding Source: 
USDA
Estimated Start of Construction: 
Fall 2019
Estimated End of Construction: 
Fall 2022
Additional Information: 

Please Note: The Burton Pond annexation will not impact the timeline or cost of the Herring Creek Project. Pumpstations are out for bid. Still need to obtain some roadway and access easements