Construction Status:
pumpstations complete, Pinewater under construction, Banks Road ready for bid
Financing Status:
Phase III financing accepted
Funding Source:
USDA
Estimated Start of Construction:
Fall 2019
Estimated End of Construction:
Fall 2022
Additional Information:
Please Note: The Burton Pond annexation will not impact the timeline or cost of the Herring Creek Project. Pumpstations are out for bid. Still need to obtain some roadway and access easements